53 Rural Road Projects Worth RM4.3 Billion Put on Hold

Published by on

Rural Road Projects Worth Rm4.3 Billion Put On Hold

Malaysia has put 53 rural road projects worth RM4.3 billion on hold following a directive from the Ministry of Finance (MOF). The projects are at different stages, with some already tendered but unable to proceed while others remain in the design or pre-qualification stages.

Key takeaways

  • 53 rural road projects worth RM4.3 billion have been deferred.
  • Seven projects have been tendered and cleared but cannot start, while 13 are at the tender pre-qualification stage.
  • Another 29 projects are still being designed, while four have their tender documents ready.
  • The affected projects are located across multiple constituencies in Peninsular Malaysia.
  • The projects remain dependent on available government allocations, with no confirmed timeline for when they can proceed.

What Happened to the Rural Road Projects?

Fifty-three rural road projects with a combined value of RM4.3 billion have been put on hold following a directive from the Ministry of Finance.

Deputy Works Minister Datuk Seri Dr Ahmad Maslan told the Dewan Rakyat that the projects are being handled by the Public Works Department (JKR) for the Ministry of Rural and Regional Development (KKDW).

The decision means the projects cannot proceed until the necessary funding allocation is available.

Expert tip: If you regularly use rural roads, do not assume that a newly announced or tendered road project will immediately improve your route. Check current road and traffic conditions before travelling, especially where existing roads are known to be in poor condition.

How Many Projects Are Affected?

The 53 projects are currently at different stages of development.

  • Seven projects have already been tendered and cleared by the procurement board but cannot begin.
  • 13 projects are at the tender pre-qualification stage.
  • 29 projects are still being designed.
  • Four projects already have their tender documents prepared.

According to Ahmad, the projects remain dependent on government allocations. Without sufficient funding, their implementation has been deferred indefinitely.

Which Areas Are Affected?

The affected projects cover numerous constituencies across Peninsular Malaysia, including Bagan Datuk, Sungai Petani, Langkawi, Mersing, Tumpat, Gua Musang, Kuala Krai, Rompin, Cameron Highlands, Jerai, Sungai Besar, Jempol, Masjid Tanah, Jasin, Ledang and Kulai.

Other affected constituencies include Port Dickson, Bachok, Pasir Puteh, Paya Besar, Jerantut, Bera, Pokok Sena, Kuala Langat, Kuala Pilah, Dungun, Alor Gajah, Kepala Batas, Gerik, Jeli, Maran, Lipis, Hulu Selangor, Kuala Selangor and Kuala Terengganu.

Two projects in the Lipis district were specifically highlighted during the Dewan Rakyat discussion. These include a road to Pos Sinderut and a road connecting the bridge at Pos Lenjang to Pos Titom.

Why Were the Projects Put on Hold?

The Works Ministry said the issue is linked to funding allocations and commitments that exceed approved budgets.

Ahmad said KKDW has 415 rural road projects, with 391 being continuing projects that began under the 12th Malaysia Plan and were carried forward into the 13th Malaysia Plan.

For 2027, KKDW had applied for RM6 billion but received RM2.28 billion, according to Ahmad.

He argued that allocations should reflect the actual costs applied for, particularly for continuing projects that are already under way.

Common mistake: Do not interpret “put on hold” as meaning that all 53 projects have been permanently cancelled. The available information indicates that the projects have been deferred and remain dependent on future funding decisions.

What Does This Mean for Motorists?

For motorists who rely on rural roads, the delay could mean that planned improvements to road connectivity and existing routes will not happen as originally expected.

This is particularly relevant for drivers who regularly travel through areas where road conditions are already a concern. Until the affected projects receive the necessary funding and proceed, motorists should continue using existing routes and take current road conditions into account when planning journeys.

Drivers should also avoid assuming that a planned road project has already been approved for construction simply because it has been announced or reached the tender stage.

What Happens Next?

The projects remain dependent on government funding allocations. Ahmad said there is currently no certainty over when the deferred projects will be allowed to proceed.

The issue has also involved different positions from the Ministry of Finance and KKDW over rural road spending and project commitments.

MOF has said there were no restrictions on KKDW's rural road allocation and that payment delays occurred because KKDW had spent beyond its approved budgets. Prime Minister Datuk Seri Anwar Ibrahim previously said rural road spending exceeded approved allocations by RM2.1 billion between 2023 and 2025.

Meanwhile, KKDW has disputed the interpretation of the spending figures, saying its rural road allocation for 2023 to 2025 was revised from about RM3.9 billion to RM6.143 billion, with RM6.108 billion spent.

For motorists, the immediate priority is to monitor official announcements rather than assume that the affected projects will proceed on a specific date.

Frequently Asked Questions

1. How many rural road projects have been put on hold?

A total of 53 rural road projects have been deferred.

2. How much are the affected rural road projects worth?

The 53 projects have a combined value of approximately RM4.3 billion.

3. Why have the rural road projects been deferred?

The projects have been deferred because their implementation depends on available government funding allocations.

4. Are the 53 rural road projects cancelled?

No confirmed permanent cancellation has been stated for all 53 projects. They have been put on hold and remain dependent on future funding decisions.

5. How many projects have already been tendered?

Seven projects have been tendered and cleared by the procurement board but cannot begin.

6. How many projects are still being designed?

Twenty-nine of the affected projects are still at the design stage.

7. Which ministry is handling the rural road projects?

The Public Works Department is handling the projects for the Ministry of Rural and Regional Development.

8. Which areas are affected by the project delays?

The affected projects are spread across numerous constituencies in Peninsular Malaysia, including Lipis, Cameron Highlands, Bagan Datuk, Kuala Krai, Gua Musang and several other areas.

9. Will the delayed projects affect motorists?

The delays may affect motorists who are expecting road upgrades or improved connectivity in areas covered by the projects.

10. When will the deferred projects resume?

There is currently no confirmed timeline for when the deferred projects will resume because they remain dependent on funding allocations.

11. Should motorists change their travel plans because of the delays?

Motorists should continue using existing roads and check current road conditions when planning journeys through affected areas.

12. Where can motorists find updates on road conditions?

Motorists should monitor official road and traffic updates before travelling, particularly during periods of heavy rain or when travelling through rural areas.


Conclusion

The government has deferred 53 rural road projects worth RM4.3 billion, with the projects currently dependent on future funding allocations. While the delays do not mean that all the projects have been permanently cancelled, there is no confirmed timeline for when they can proceed.

For motorists, the safest approach is to continue relying on existing routes, monitor road conditions and wait for official updates before assuming that planned road improvements will be completed.

Stay informed about major road and infrastructure developments in Malaysia so you can plan safer and more reliable journeys.


Read More: Batang Lupar Bridge 2 Opens in Sarawak, Cutting Travel Time From 1 Hour to 25 Minutes


Looking to sell your car? Get a competitive offer and simplify your car-selling journey with Motorist.

Download the Motorist App now. Designed by drivers for drivers, this all-in-one app lets you receive the latest traffic updates, access live traffic cameras, and manage vehicle-related matters.

0 Comments